Early spring and winter traditionally are heavy periods for US refinery maintenance. But refiners are planning more upgrades than usual in the first half of 2019 to avoid fall and winter shutdowns as they prepare to meet coming
“They will push (winter) turnarounds later into 2020 to take advantage of that margin bump from the switch to IMO 2020,” said Susan Bell, a senior associate at energy consultancy IHS Markit.
BP is shutting one of two small CDUs at its 413,500 bpd Whiting, Indiana, refinery on Monday for 30 days of work. The Whiting refinery is BP’s largest in North America.
Work also is continuing this month on a planned
Two other major overhauls finished during the switchover between the quarters.
Exxon Mobil Corp recently finished CDU overhauls at two plants: its 560,500 bpd Baytown, Texas, refinery wrapped up work on its largest CDU in late March and the company’s 502,500